Bushey Cemetery - Progress

Works are progressing well on site with the Zinc roofs to the Prayer Halls coming to a completion, the bare root plants having just arrived are already being planted despite the current cold weather. Works to the North Field (in the distance) are almost complete with just the final bare root planting to take place.

The timber colonnade structures are already complete with the larch soffit cladding currently being installed and the “green roofs” just waiting for the wild flower pre-seeded mats to be laid. Block paving around the building is also underway with the already completed road ways providing suitable storage area for the block paving.

Client: The United Synagogue
 

 
Architect: Waugh Thistleton
 

 
QS: Deacon & Jones
 

 
Value: £6.1m
 

 
Duration: 78 Weeks