Making good progress at our project at Northgate Square - Crawley, with the erection of the RC frame well underway.

Works completed in the last month

Installation of the Welfare accommodation. Erection of tower crane Ground floor concrete slab Rear car-park infrastructure Concrete slab to 1st floor Surface water and Sewer connections Formation of scaffold base

Summary of works for the next two months

Completion of all infrastructures Install service for future provision Installation 1st floor transfer slab Concrete frame to 4th floor level Procurement of main service connections

The £16m new build development will create 33 no. 1 bed apartments, 60 no. 2 bed apartments and 5 no. 3 bed apartments - totalling 98 residential units.


In addition we will be carrying out hard and soft landscaping, creation of a car park and bicycle storage, as well as, a roof terrace on the sixth floor for use by private residents.