Making good progress at our project at Northgate Square - Crawley, with the erection of the RC frame well underway.
Works completed in the last month
Installation of the Welfare accommodation.
Erection of tower crane
Ground floor concrete slab
Rear car-park infrastructure
Concrete slab to 1st floor
Surface water and Sewer connections
Formation of scaffold base
Summary of works for the next two months
Completion of all infrastructures
Install service for future provision
Installation 1st floor transfer slab
Concrete frame to 4th floor level
Procurement of main service connections
The £16m new build development will create 33 no. 1 bed apartments, 60 no. 2 bed apartments and 5 no. 3 bed apartments - totalling 98 residential units.
In addition we will be carrying out hard and soft landscaping, creation of a car park and bicycle storage, as well as, a roof terrace on the sixth floor for use by private residents.