Making good progress at our project at Northgate Square - Crawley, with the erection of the RC frame well underway.

Works completed in the last month

Installation of the Welfare accommodation.
 

 
Erection of tower crane
 

 
Ground floor concrete slab
 

 
Rear car-park infrastructure
 

 
Concrete slab to 1st floor
 

 
Surface water and Sewer connections
 

 
Formation of scaffold base

Summary of works for the next two months

Completion of all infrastructures
 

 
Install service for future provision
 

 
Installation 1st floor transfer slab
 

 
Concrete frame to 4th floor level
 

 
Procurement of main service connections

The £16m new build development will create 33 no. 1 bed apartments, 60 no. 2 bed apartments and 5 no. 3 bed apartments - totalling 98 residential units.

In addition we will be carrying out hard and soft landscaping, creation of a car park and bicycle storage, as well as, a roof terrace on the sixth floor for use by private residents.